Andershaw Wind Farm is located to the South of Glasgow in South Lanarkshire, Scotland. It began construction in 2015 and is expected to be operational in late 2016.

Key Facts

Number of Turbines

11

Capacity

36.3mw

Equivalent homes served

19,200*

Andershaw Wind Farm Location

Preparatory works began in late 2015 and our access tracks are now in place ahead of turbine deliveries. The next project milestone scheduled is the construction of the turbine foundations and site substation which are expected to be completed by June 2016. This will be followed by the delivery and installation of the turbines which are due to be completed in October 2016.

Construction timetable

  • Preparator & Infrastructure Works:
    October 2015 – June 2016
  • Turbine Delivery: July – August 2016
  • Erection of Turbines and commissioning:
    August – October 2016
  • Operational: Late 2016